QUESTION 21

- (Topic 2)
All of the following are resources that need to be monitored and controlled except for which one?

Correct Answer: C

QUESTION 22

- (Topic 2)
Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

Correct Answer: A

QUESTION 23

- (Topic 3)
During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Correct Answer: C

QUESTION 24

- (Topic 4)
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

Correct Answer: D

QUESTION 25

- (Topic 1)
Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Correct Answer: A