QUESTION 56

- (Topic 3)
You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?

Correct Answer: B

QUESTION 57

- (Topic 2)
You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Correct Answer: C

QUESTION 58

- (Topic 4)
Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?

Correct Answer: A

QUESTION 59

- (Topic 1)
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental
benefits?

Correct Answer: D

QUESTION 60

- (Topic 3)
Which of the following tools/techniques keep program managers and executives informed
of the program's progress?

Correct Answer: C