QUESTION 46

- (Topic 3)
You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?

Correct Answer: C

QUESTION 47

- (Topic 1)
A knowledge area defines a subset of program management and its processes within that
domain. For example, the knowledge area of quality management includes the processes related directly to quality management only. Which knowledge area ensures that all knowledge areas interact correctly with one another?

Correct Answer: C

QUESTION 48

- (Topic 1)
You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Correct Answer: B

QUESTION 49

- (Topic 1)
You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?

Correct Answer: C

QUESTION 50

- (Topic 2)
You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?

Correct Answer: A