QUESTION 66

A major strategic change has occurred and you are managing the change at portfolio level. You are currently performing gap analysis and you receive information on a stakeholder that is extremely unhappy with how the change will be handled in your portfolio. What should be your best course of action?

Correct Answer: D

QUESTION 67

Portfolio managers tend to use the efficient frontier analysis as a modeling approach that gives decision makers the analytical tool to optimize portfolios given resource constraints such as risk. Consider that your company is risk-averse, on which side of the efficient frontier curve should the undertaken portfolios lie?

Correct Answer: B

QUESTION 68

Your online ordering company wants to add a component to its portfolio that its sponsor believes will outdistance the competition, but it has risks and also will be subject to regulatory approval. The purpose is to use parachutes to deliver the merchandise ordered through small helicopters so the recipients receive their orders within three hours of the on line purchase. As the portfolio manager you recognize this component is a major change and will require resources if it is approved. You are now performing change management using a change structure that:

Correct Answer: B

QUESTION 69

You are the manager of a major portfolio with a variety of stakeholders and stakeholder groups. you know that managing communication is key to success and you stress on maintaining a high communication level. You want to start developing your Communication Management Plan and are planning to use

Correct Answer: B

QUESTION 70

Your probability and impact assessment work is complete, and you are using the results to prepare the portfolio risk management plan. As you do so, it also is useful to:

Correct Answer: A