QUESTION 61

In a portfolio you have a continuous interaction between the portfolio and its components. The approach is top down when it comes to offering guidelines and approaches and becomes bottom up when the components report status and progress to the portfolio. Metrics are used for measuring the performance. They need to be meaningful in order to be able to provide clear and logical targets, and in order to be able to be measured. Which guideline is used in order to develop meaningful measures?

Correct Answer: B

QUESTION 62

Risks perspectives differ within the organization between executive management, operations management, portfolio management and project/program management. When it comes to Operations management, which of the following is a risk concern?

Correct Answer: A

QUESTION 63

All measurements in a Portfolio are done in correspondence to Key Performance Indicators (KPIs), and defining those KPIs is essential and should be done by highly capable personnel. Which of the following is true regarding who prepares KPIs and which party approves them?

Correct Answer: C

QUESTION 64

You are managing a portfolio for your company and are trying to balance the tasks that will be done internally based on the availability and the ones that will be outsourced. Managing supply and demand is a recurring activity in the portfolio life cycle and results in changes in resource utilization and resource efficiency. What is the expected outcome from managing supply and demand?

Correct Answer: B

QUESTION 65

Your organization has a defined portfolio management process that it has followed for three years. As the portfolio manager, you keep your various plans up to date, and because of numerous regulatory changes involving the telecom industry, it is time to review and update the risk management plan. You have several key stakeholders working with you as you realize the importance of this plan in maintaining a competitive advantage. One way you and your team are assessing the various risks that may impact the structure of the portfolio is to use:

Correct Answer: C