Steven, the Scrum Master, is approached by one of the Development Team members saying that they are not completing regression tests for all of the work they are performing to the level defined in the Definition of Done. They have discussed this with the Product Owner and decided to remove regression testing from the Definition of Done.
Which two actions are the most appropriate for Steven to take? (Choose two.)
Correct Answer:
CD
As a servant/leader, the Scrum Master facilitates conversations through open ended QUESTION NO:s in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.
According to Scrum theory, how should a group of fifty people be divided into multiple Development Teams?
Correct Answer:
B
During the Sprint Review of a scaled development effort, each Scrum Team should demonstrate its individual Increment in a separate branch of the code.
Correct Answer:
B
If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of “Done”. Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.
Which Scrum Value is impacted by trust?
Correct Answer:
F
Without trust, team members will have difficulties acting and behaving in the ways that reflect the Scrum values and how effective they apply empiricism.
What is the Development Team responsible for?
Correct Answer:
C