Steven, who is a Scrum Master, on one of the Scrum Teams has approached you asking for advice. Their Daily Scrum requires more than 15 minutes and the team has suggested dividing themselves into two separate teams in order to stay within the time box.
As another Scrum Master, what would be the best response?
Correct Answer:
C
The relationship between cause and effect can become more clear when more information emerges.
Multiple Scrum Teams working from the same Product Backlog must have the same Sprint start dates.
Correct Answer:
B
Multiple Scrum Teams could have the same Sprint start dates but it is not mandatory as the importance is on being able to integrate their shippable Increments at the end of their Sprints.
Your organization has formed a new Scrum Team and has assigned you as the Scrum Master. In what ways would you help the team start?
Correct Answer:
B
Scrum Teams should have all of the competencies and skills to do the work in the Product Backlog which includes understanding the goals and history of the product and ensuring that they all know what “done” means.
What would be typical Scrum Master activities during the Sprint?
Correct Answer:
B
Which of the following are feedback loops in Scrum?
Correct Answer:
A