Who can cancel a Sprint? (choose the best answer)
Correct Answer:
D
According to the Scrum Guide, the Product Owner can cancel a Sprint, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the Product Owner.
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)
Correct Answer:
CEF
The correct answers are C, E, and F, because these phrases best describe the purpose of a definition of “Done”. It creates transparency over the work inspected at the Sprint Review, as it defines what it means for an Increment to be potentially releasable. It guides the Development Team in creating a forecast at the Sprint Planning, as it helps them estimate how much work they can accomplish in a Sprint. It defines what it takes for an Increment to be ready for release, as it ensures that the product meets the quality expectations of the stakeholders.
The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?
Correct Answer:
C
According to the Scrum Guide1, ordering Product Backlog items is solely up to the Product Owner’s discretion. The Product Owner orders items in the Product Backlog to best achieve goals and missions. To do this, they optimize value by considering various factors such as cost and benefit, risk, dependencies, date needed, etc. The Product Owner is responsible for maximizing the value of the work the Development Team does. The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide. They do this by helping everyone understand Scrum theory and practice, both within the Scrum Team and the organization. Therefore, an appropriate action for the Scrum Master to take if the Product Owner is struggling with ordering the Product Backlog is to offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
References: Scrum Guide
The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)
Correct Answer:
A
The Scrum Master should talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review, as stated in [5]: “The Scrum Master should educate the IT manager about how Scrum works and how progress is measured. The Scrum Master should invite the IT manager to attend the Sprint Review where the Development Team demonstrates what was accomplished during the Sprint. The Scrum Master should also explain that status reports are not necessary in Scrum, as transparency is ensured by using artifacts such as Product Backlog, Sprint Backlog, and Increment.”
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)
Correct Answer:
BC
The correct answers are B and C, because these are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity. The Scrum Guide states that “the Scrum Master serves the Development Team in several ways, including … removing impediments to the Development Team’s progress; facilitating Scrum events as requested or needed; and coaching the Development Team in self-organization and cross-functionality.” Therefore, by removing impediments and facilitating decisions, the Scrum Master helps the Development Team focus on their work and deliver value.