Which two ways of creating Development Teams are consistent with Scrum’s values? (Choose two.)
Correct Answer:
AD
Who starts the Daily Scrum?
Correct Answer:
B
Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)
Correct Answer:
B
Which two things should the Development Team do during the first Sprint? (Choose two.)
Correct Answer:
CE
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
Correct Answer:
A