Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)
Correct Answer:
BCE
At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What
factors likely led to this? (Choose two.)
Correct Answer:
AB
Why does the Product Owner want the Development Team to adhere to its definition of “Done”?
Correct Answer:
A
What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply? (Choose the best two answers.)
Correct Answer:
AB
The length of a Sprint should be:
Correct Answer:
D