QUESTION 66

What is the function or purpose of management in Scrum? (choose the best answer)

Correct Answer: B
The correct answer is B. To present the Scrum Teams with insights and resources that help them improve. According to the Scrum Guide1, “The role of management in Scrum is to support the Product Owner with insights and information into high-value product and system capabilities.” Management also helps the Scrum Team by providing an environment that fosters agility, learning, and collaboration2. Management does not directly control or monitor the work of the Developers, nor does it interfere with the self-organization and autonomy of the Scrum Team3. Management’s function in Scrum is to enable and empower the Scrum Team to deliver value and continuously improve.

QUESTION 67

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

Correct Answer: B
According to the Scrum Guide, estimates are made by the people doing the work, which is the Development Team. The Development Team is responsible for all estimates in the Product Backlog and the Sprint Backlog. The other options are not valid guidelines for estimating work in Scrum, as they are either too prescriptive (such as requiring story points or relative units), incorrect (such as forbidding estimating or having the Product Owner make estimates), or unnecessary (such as checking estimates with the Development Team).

QUESTION 68

What may be included in the Sprint Backlog? (choose the best answer)

Correct Answer: E
According to the Scrum Guide, the Sprint Backlog may include any items that are a decomposition of the selected Product Backlog items, such as user stories, tasks, use cases, tests, or others. The Sprint Backlog is the Developers’ plan for the Sprint, and it contains all the work that they forecast they can do to achieve the Sprint Goal and create a “Done” Increment. The other options are not valid, as they are either too specific (such as user stories or tasks) or too vague (such as tests).

QUESTION 69

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

Correct Answer: D

QUESTION 70

Who is responsible for tracking the remaining work of the Sprint?

Correct Answer: A