PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 286

- (Topic 1)
In which process group is the scope first defined?

Correct Answer: A

QUESTION 287

- (Topic 3)
Which type of estimating is used to improve the accuracy of an activity's duration?

Correct Answer: C

QUESTION 288

- (Topic 1)
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

Correct Answer: A

QUESTION 289

- (Topic 2)
The following is a network diagram for a project.
PMP dumps exhibit
The total float for the project is how many days?

Correct Answer: B

QUESTION 290

- (Topic 2)
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Correct Answer: A