PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 21

Acompany routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.
How can the project manager address this challenge to assure outsourced vendors deliver?

Correct Answer: C

QUESTION 22

A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.
What should the project manager do?

Correct Answer: C

QUESTION 23

A self-organizing team for a critical project is consistently delivering value according to their commitments.
During a retrospective, the project manager observed that most of the team members were stressed due to over commitments. What should the project manager do?

Correct Answer: A

QUESTION 24

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?

Correct Answer: D

QUESTION 25

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.
What should the project manager do to improve the situation?

Correct Answer: D