QUESTION 226

- (Topic 3)
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Correct Answer: C

QUESTION 227

- (Topic 2)
At which stage of the project should certain factors such as the unavailability of human resources due to constraint be considered?

Correct Answer: C

QUESTION 228

- (Topic 1)
An input required to develop a preliminary project scope statement is:

Correct Answer: B

QUESTION 229

- (Topic 4)
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Correct Answer: D

QUESTION 230

- (Topic 2)
During which process group is the quality policy determined?