- (Topic 5)
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Correct Answer:
A
- (Topic 3)
An imposed date for completion of the project by the customer is an example of a project:
Correct Answer:
C
- (Topic 3)
An intentional activity to modify a nonconforming product or product component is called:
Correct Answer:
A
- (Topic 1)
Which of the following tools and techniques is used in the Verify Scope process?
Correct Answer:
A
- (Topic 5)
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
Correct Answer:
B