Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.
What should the project manager do?
Correct Answer:
D
A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.
What should the project manager do in this situation?
Correct Answer:
D
A team member who is working on a critical project deliverable reported that their computer is not working.
The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.
How should the project manager address this situation?
Correct Answer:
C
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
Solution:
A picture containing chart Description automatically generated
Does this meet the goal?
Correct Answer:
A
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.
Which approach should the project manager use in this situation?
Correct Answer:
A