PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 191

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.
How should the project manager deal with the situation?

Correct Answer: D

QUESTION 192

There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following should be regarded with the highest priority?

Correct Answer: A

QUESTION 193

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.
What should the project manager do?

Correct Answer: C

QUESTION 194

A project manager has been approached by the project sponsor about adding to the project scope How should the project manager accommodate this request?

Correct Answer: D

QUESTION 195

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?

Correct Answer: C