PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 186

- (Topic 3)
The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?

Correct Answer: B

QUESTION 187

- (Topic 4)
When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?

Correct Answer: A

QUESTION 188

- (Topic 4)
Funding limit reconciliation is a tool and technique used in which process?

Correct Answer: B

QUESTION 189

- (Topic 3)
In which process might you use risk reassessment as a tool and technique?

Correct Answer: B

QUESTION 190

- (Topic 1)
In which process group is the scope first defined?

Correct Answer: A