PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 176

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?

Correct Answer: C

QUESTION 177

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

Correct Answer: A

QUESTION 178

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.
What should the project manager do to keep the stakeholders engaged?

Correct Answer: D

QUESTION 179

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Correct Answer: B

QUESTION 180

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project manager do to avoid this in the future?

Correct Answer: D