PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 166

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.
What should the project manager do?

Correct Answer: C

QUESTION 167

A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.
The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.
What should the project manager do?

Correct Answer: A

QUESTION 168

During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)

Correct Answer: BD

QUESTION 169

A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to enhance the budget estimations for the project?

Correct Answer: B

QUESTION 170

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer.
What should the project manager do?

Correct Answer: A