PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 161

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems. What should the project manager do next?

Correct Answer: B

QUESTION 162

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?

Correct Answer: C

QUESTION 163

A project schedule risk has turned into an issue. The project manager foresees delays in project execution. What should the project manager do to resolve the issue?

Correct Answer: C

QUESTION 164

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.
What is the project manager doing?

Correct Answer: B

QUESTION 165

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)

Correct Answer: BE