PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 141

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

Correct Answer: A

QUESTION 142

A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client's needs.
Which factor should the project manager have considered when developing the product?

Correct Answer: C

QUESTION 143

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.
What kind of leadership style should the project manager utilize for the current project?

Correct Answer: A

QUESTION 144

A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face meetings.
How should the project manager approach this situation?

Correct Answer: B

QUESTION 145

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.
What should the project manager do next?

Correct Answer: A