PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 136

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?

Correct Answer: C

QUESTION 137

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

Correct Answer: B

QUESTION 138

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.
How should the project manager handle this situation?

Correct Answer: C

QUESTION 139

A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that worked well for previous projects. However, a few team members are not happy with this plan.
What should the project manager have done to avoid this?

Correct Answer: B

QUESTION 140

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?

Correct Answer: C