An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.
What should the project manager do to help the project team?
Correct Answer:
A
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
Correct Answer:
A
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
Correct Answer:
B
A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they accepted an offer from another firm. What should the project manager do next?
Correct Answer:
A
An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-ofsupport date for the database platform. Anew impediment now implies the need to continue use of the old platform another year at a higher support price.
What should the product owner do about this situation?
Correct Answer:
C