PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 111

- (Topic 1)
The initial development of a Project Scope Management plan uses which technique?

Correct Answer: C

QUESTION 112

- (Topic 4)
What cost control technique is used to compare actual project performance to planned or expected performance?

Correct Answer: D

QUESTION 113

- (Topic 3)
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

Correct Answer: B

QUESTION 114

- (Topic 4)
Whose approval may be required for change requests after change control board (CCB) approval?

Correct Answer: C

QUESTION 115

- (Topic 3)
Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?

Correct Answer: B