PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 106

- (Topic 3)
Which of the following are inputs into the Administer Procurements process?

Correct Answer: C

QUESTION 107

- (Topic 2)
When does the project team determine which dependencies are discretionary?

Correct Answer: D

QUESTION 108

- (Topic 2)
Which type of organizational structure is displayed in the diagram provided?
PMP dumps exhibit

Correct Answer: B

QUESTION 109

- (Topic 3)
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Correct Answer: A

QUESTION 110

- (Topic 4)
When cost variance is negative and schedule variance is positive, the project is:

Correct Answer: B