PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 86

A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables. What should the project manager do?

Correct Answer: D

QUESTION 87

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.
During the iteration retrospective, the team realizes that the complexity of the work was underestimated. What should the project manager do?

Correct Answer: B

QUESTION 88

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work. What should the project manager do next to fulfill this resource need?

Correct Answer: A

QUESTION 89

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations? (Choose two)

Correct Answer: AD

QUESTION 90

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones.
This led to some misunderstandings among team members. The project sponsor has allocated a monetary award. How should the project manager utilize the award?

Correct Answer: C