PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 81

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

Correct Answer: A

QUESTION 82

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.
What should the project manager do to keep the stakeholders engaged?

Correct Answer: D

QUESTION 83

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Correct Answer: B

QUESTION 84

A project manager starts to receive emails from different stakeholders requesting information about the project status. What should the project manager do to avoid this in the future?

Correct Answer: D

QUESTION 85

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks
Drag each risk type on the left to its correct example on the right
PMP dumps exhibit
Solution:
PMP dumps exhibit

Does this meet the goal?

Correct Answer: A