PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 66

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?

Correct Answer: C

QUESTION 67

A project schedule risk has turned into an issue. The project manager foresees delays in project execution. What should the project manager do to resolve the issue?

Correct Answer: C

QUESTION 68

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.
What is the project manager doing?

Correct Answer: B

QUESTION 69

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)

Correct Answer: BE

QUESTION 70

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.
What should the project manager do?

Correct Answer: C