PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 56

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project manager do to ensure business value is delivered early?

Correct Answer: D

QUESTION 57

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected. What should the project manager do?

Correct Answer: A

QUESTION 58

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months. What should the project manager do first?

Correct Answer: A

QUESTION 59

A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the company's core working hours begin at 9:00 a.m.
What should the project manager have done to prevent this situation?

Correct Answer: C

QUESTION 60

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion. What should the project manager do?

Correct Answer: C