PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 51

A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.
However, that tool is not available in one team member's country. How should the project manager deal with this situation?

Correct Answer: D

QUESTION 52

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.
What should the project manager do to address this situation?

Correct Answer: B

QUESTION 53

Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?

Correct Answer: C

QUESTION 54

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

Correct Answer: A

QUESTION 55

A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After discussing these concerns with the team, it is determined that the project does not have the full support of senior management.
What should the new project manager do next?

Correct Answer: C