PMP Dumps

PMP Free Practice Test

PMP PMP: Project Management Professional

QUESTION 1

A stressful situation has presented some challenges for the team. The project manager notices stress behavior in some of the team members, and it is beginning to spread across the group. The project manager needs to coach the team to change their mindset in order to be more efficient.
What should the project manager do?

Correct Answer: D

QUESTION 2

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.
What should the project manager do?

Correct Answer: B

QUESTION 3

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to analyze team performance? (Choose two)

Correct Answer: DE

QUESTION 4

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?

Correct Answer: B

QUESTION 5

Drag the items on left side to the matching term within the correct project approach on the right side.
PMP dumps exhibit
Solution:
Graphical user interface, application Description automatically generated

Does this meet the goal?

Correct Answer: A