PMI-SP Dumps

PMI-SP Free Practice Test

PMI PMI-SP: PMI Scheduling Professional Practice Test

QUESTION 31

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

Correct Answer: A
The project calendar needs to be updated to reflect the 24-hour time period rather than the 8-hour time period. The project calendar is used to define the working and nonworking days and times for tasks. This calendar is usually used to represent an organization's traditional working hours. Project uses this calendar to schedule tasks that do not have resources assigned or that have a task type of fixed duration. By default, the Standard base calendar is used as the project calendar. A user can also reflect alternative schedules by using other base calendars. The working days and hours in the project calendar reflect the working days and hours for the whole project. A user can also specify special days off, such as company holidays. A user can also indicate other nonworking times to reflect periods when the whole team will be working on nonproject activities, such as company meetings or department retreats.
Answer option D is incorrect. The schedule management plan will reference to the project calendar and the resource calendar. It does not need to be updated directly as a result of the time period change.
Answer option C is incorrect. The resource calendar does not need to be updated as this document defines when resources are available.
Answer option B is incorrect. The activities of the project are not changing, only the time periods of the project calendar.

QUESTION 32

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Correct Answer: C
The communications management plan will define who will receive what information. Answer option B is incorrect. The project sponsor may be a recipient but the project communications management plan is the best selection.
Answer option A is incorrect. Functional management is not the best choice in a projectized structure.
Answer option D is incorrect. The project customer may receive a copy of the report, but the project communications management plan should direct the communications.

QUESTION 33

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

Correct Answer: D
Of all the choices, the best explanation is that a dashboard is a report for quick review of the project's performance metrics. While there are some software solutions, they still focus on the key performance criteria of the project.
Answer option C is incorrect. This answer defines the definition of quality control, not the dashboard's review of project performance.
Answer option B is incorrect. Dashboards focus on the performance of the project's key performance factors, not the project manager.
Answer option A is incorrect. A status report could include the details of the project's risks and issues, but usually not the dashboard.

QUESTION 34

Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

Correct Answer: B
All scope changes should also be updated in the project scope baseline. The scope baseline is the project scope statement, work breakdown structure (WBS), and the WBS dictionary.
Answer option D is incorrect. If the changes affect cost then the cost baseline would also be updated. The question did not indicate that therbe would a change in the project cost. Answer option C is incorrect. Quality control does not change. It always reflects the demands of the project scope.
Answer option A is incorrect. The project final report evaluates the success and failures of the project scope.

QUESTION 35

Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance indexes of your project. The schedule performance index (SPI) of your project is 1.325. What does this figure indicate?

Correct Answer: A
According to the question, the SPI of your project is 1.325. This figure is greater than 1. Hence, it shows that the schedule performance is better than expected. What is SPI? Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.
Answer option C is incorrect. SPI has nothing to do with cost performance.
Answer options B and D are incorrect. An SPI value less than 1 or 0 indicates that the schedule performance is either below expectation or is right on target.