PMI-SP Dumps

PMI-SP Free Practice Test

PMI PMI-SP: PMI Scheduling Professional Practice Test

QUESTION 81

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

Correct Answer: B
Apportioned effort is effort applied that you cannot subdivide into work packages, but it is related to, usually in a supportive role, to the completion of the project work packages. The project management overhead, such managing the project work, is an example of apportioned effort. Apportioned effort (AE) is the effort that is applied to the project-related work that cannot be easily and readily divided into discrete efforts for those tasks, but which is associated in a direct proportion to the discrete work efforts that are capable of being measured. The presence of apportioned effort relies particularly on the performance of further efforts.
Answer option C is incorrect. This is an example of discrete effort.
Answer option A is incorrect. This is an example of a scope change that has not been approved.
Answer option D is incorrect. This is an example of a scheduling technique.

QUESTION 82

Which of the following provides a method to track project progress during project execution against what was planned?

Correct Answer: C
A schedule baseline provides a method to track project progress during project execution against what was planned. What is schedule baseline? Schedule baseline is a project schedule used in measuring project progress. It helps provide a comparison with the actual progress of work against the schedule and to determine if performance to date is within acceptable parameters. Any change caused by change in scope of the project invalidates the original schedule and requires a new baseline schedule.
Answer options D, A, and B are incorrect. A detailed project budget, team members profile,
and benefit-cost ratio will not help you track project progress. What is BCR? A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that attempts to summarize the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or proposal, expressed in monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should be expressed in discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar expended.

QUESTION 83

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

Correct Answer: D
A make-or-buy analysis is used to verify whether a particular work can best be accomplished by the project team or must be purchased from outside sources. The budget constraints can influence the make-or-buy decisions. A make-or-buy analysis must consider all related costs; both direct and indirect support costs.
Answer option B is incorrect. Expert judgment is a technique based on a set of criteria that has been acquired in a specific knowledge area or product area. It is obtained when the project manager or project team requires specialized knowledge that they do not possess. Answer option A is incorrect. The type of contract to be used and the specific contract terms and conditions fix the degree of risk being assumed by the buyer and seller.
Answer option C is incorrect. Negotiations clarify the structure, requirements and other terms of the purchase so that the mutual agreement can be reached prior to signing the contracts.

QUESTION 84

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?

Correct Answer: B
The schedule baseline is the only output of the develop schedule process among these answers. The three other outputs of the Develop Schedule Process are: project schedule, schedule data, and project document updates.
Answer option D is incorrect. Activity duration estimates are an output of the Estimate Activity Duration process.
Answer option A is incorrect. Work performance information is an input of the Control Schedule process.
Answer option C is incorrect. Resource calendars are an input to the Develop Schedule process.

QUESTION 85

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:
PMI-SP dumps exhibit
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

Correct Answer: D
The path of ABDHJ will take 21 days to complete and cannot exceed 27 days or else the project will be late. If Activity B takes four additional days and Activity D takes two additional days, this adds (4+2= 6) six days to the path, bringing the path's duration to exactly (21+6 = 27) twenty seven days. There is no available float left for Activity E or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates.
Answer options A, C, and B are incorrect. There is no float available because the path's duration has increased to 27 days.