QUESTION 51

Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?

Correct Answer: D
According to the PMBOK, the project manager provides the feedback to programs and portfolios by means of status reports and change requests that may impact other projects, programs, or portfolios. The needs of the projects, including the resource needs, are rolled up and communicated back to the portfolio level, which in turn sets the direction for organizational planning. What is a status report? A status report is a narrative description
about a subject that is relevant to an organization. Typically, a user submits a status report that was created for him by a manager. He can also create and submit his own unrequested status report at any time. It is a collaborative feature specific to PWA. Status report in PWA is a convenient way to exchange textual information with the team members about the status of a project or items in addition to task progress, which a user updates on the Tasks page. What are change requests? Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented.
Answer option C is incorrect. While regular communication is needed, this is not the best answer for the question.
Answer option A is incorrect. Status meetings are a part of project communications, but do not answer the question as completely as status reports and change requests.
Answer option B is incorrect. Push communications is one type of communicating mode where the project manager pushes the information to recipients. This is not the best choice for the question because there are other modes communicating as well.

QUESTION 52

Adrian is the project manager for her project. This new project needs to identify all the
stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

Correct Answer: D
Stakeholders are interviewed and can help identify other stakeholders that should be included in the project communications.
Answer option B is incorrect. According to the PMBOK, this is not the best answer. Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by it.
Answer option C is incorrect. Project customers are stakeholders.

QUESTION 53

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:
PMI-SP dumps exhibit
Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Correct Answer: D
If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date. What is float?
Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates.
Answer options A, B, and C are incorrect. These are not valid answers for the question.

QUESTION 54

You work as a Project Manager for Tech Perfect Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:
PMI-SP dumps exhibit
What will be the cost variance (CV) of the project at the current point of time?

Correct Answer: B
According to the question, you are required to calculate the cost performance index (CPI) of the project. Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is calculated based on the following formula: CV = Earned Value (EV) - Actual Cost (AC) A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than originally planned for the project. Now, putting the provided values in the formula: CV = EV - AC = 320 - 400 = -80 As the value of CV (which is -80) is negative, it shows that the costs are higher than that have been planned for the project. What is BCWP (or EV)? Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is the budgeted amount for the work actually completed on the schedule activity during a given time period. What is BCWS (or PV)? Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component. What is ACWP (or AC)? Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity. It is the cost of the work to date, including direct and indirect costs. AC is money that has actually been expended to date.

QUESTION 55

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

Correct Answer: A
The communications management plan defines who needs what information, when the information is needed, and the modality the information is expected in.
Answer option C is incorrect. The project schedule could include project management activities such as schedule communication, but the communications management plan is the best answer as this information is absolutely documented in this plan.
Answer option D is incorrect. The schedule management is not the best location for this information.
Answer option B is incorrect. The request for customer communication is not an issue, so this choice is not the most appropriate.