PMI-RMP Dumps

PMI-RMP Free Practice Test

PMI PMI-RMP: PMI Risk Management Professional

QUESTION 71

You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?

Correct Answer: B

QUESTION 72

Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?

Correct Answer: B

QUESTION 73

Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?

Correct Answer: B

QUESTION 74

You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're
your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

Correct Answer: C

QUESTION 75

Which of the following risk responses delineates that the project plan will not be changed to deal with the risk?

Correct Answer: C