The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote
Which decision role was used?
Correct Answer:
D
A business analyst is reviewing a discrepancy report after a test session. The discrepancy report has revealed a defect that the business analyst must address. Which of the following criteria should the business analyst use to identify the appropriate response to the defective test result?
Correct Answer:
C
A business analyst has been assigned to a project team that is redesigning the company's website The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?
Correct Answer:
A
Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:
Correct Answer:
A
The customer and Ihe business analyst are collaborating in the development of a solution scope. It is important for the customer to:
Correct Answer:
C