Company A has initialed a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder. is excluded from the list of stakeholders.
In which reference matenal can the business analyst find information about the missing project stakeholders?
Correct Answer:
B
A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.
What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will need to have a discussion about the budget?
Correct Answer:
B
After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:
Correct Answer:
A
The quality function deployment is best suited to assist in the process of:
Correct Answer:
C
After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule The business analyst needs to review the amount of work
the team is capable of delivering based on the approved project schedule. Which prioritization technique should the business analyst use?
Correct Answer:
A