QUESTION 11

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

Correct Answer: D

QUESTION 12

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.
Which of the following techniques would the business analyst use to identify stakeholders?

Correct Answer: A

QUESTION 13

For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

Correct Answer: D

QUESTION 14

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Correct Answer: C

QUESTION 15

Whjch tool provides combined functionality for business analysis and quality assurance activities?

Correct Answer: B