PMI-PBA Dumps

PMI-PBA Free Practice Test

PMI PMI-PBA: PMI Professional in Business Analysis (PMI-PBA)

QUESTION 6

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.
Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

Correct Answer: C

QUESTION 7

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.
How should the business analyst obtain approval?

Correct Answer: B

QUESTION 8

The requirements traceability matrix should primarily be used to:

Correct Answer: D

QUESTION 9

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible. Which activity should the business analyst initiate before beginning requirements elicitation?

Correct Answer: A

QUESTION 10

A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in
a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?

Correct Answer: A