After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:
Correct Answer:
A
The quality function deployment is best suited to assist in the process of:
Correct Answer:
C
After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule The business analyst needs to review the amount of work
the team is capable of delivering based on the approved project schedule. Which prioritization technique should the business analyst use?
Correct Answer:
A
A business analyst is trying to determine which analysis technique will be best suited to elicit information from a large number of users in a short period of time. Which elicitation technique is best suited for this purpose?
Correct Answer:
C
Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?
Correct Answer:
C