QUESTION 21

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good.
What should the agile team lead do?

Correct Answer: D

QUESTION 22

After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?

Correct Answer: C

QUESTION 23

During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?

Correct Answer: B

QUESTION 24

An agile team has only one database administrator with the necessary knowledge of database-related tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?

Correct Answer: C

QUESTION 25

A customer and a product delivery team meet to discuss a products attributes goals, expectations, hypothesis, and high-level needs What is a benefit of this meeting?

Correct Answer: C