QUESTION 61

Following chart lists stories for a release of an Agile project;
PMI-ACP dumps exhibit
If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?

Correct Answer: A

QUESTION 62

What is the responsibility of an extreme Programming (XP) customer role?

Correct Answer: B

QUESTION 63

A value stream map is a tool used to identify the:

Correct Answer: A

QUESTION 64

What is the common communication bridge between the team and the Product Owner?

Correct Answer: B

QUESTION 65

What key benefits might stakeholders realize from an Agile approach?

Correct Answer: B