During the review session, the product owner discovers that the user interface has a response time of 10 seconds The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.
What should have been done to avoid this?
Correct Answer:
A
A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?
Correct Answer:
D
The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?
Correct Answer:
C
Spike solutions are appropriate when:
Correct Answer:
D
The velocity chart, storyboard, burndown chart, and impediment list are often communicated using:
Correct Answer:
B