- (Topic 2)
Which items are an output of the Perform Integrated Change Control process?
Correct Answer:
C
- (Topic 4)
The process of identifying the stakeholders' information needs is completed during:
Correct Answer:
A
- (Topic 1)
A tool or technique used in the Control Procurements process is:
Correct Answer:
B
- (Topic 2)
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
Correct Answer:
D
- (Topic 1)
Which process determines the risks that may affect the project and documents their characteristics?
Correct Answer:
D