PMI-100 Dumps

PMI-100 Free Practice Test

PMI PMI-100: CAPM (Certified Associate in Project Management) Exam

QUESTION 16

- (Topic 4)
Which is a communication method used in the Report Performance process?

Correct Answer: D

QUESTION 17

- (Topic 4)
Which of the following is an output of the Distribute Information process?

Correct Answer: C

QUESTION 18

- (Topic 2)
In the Define Activities process, the schedule management plan is used to:

Correct Answer: D

QUESTION 19

- (Topic 2)
A risk that arises as a direct result of implementing a risk response is called a:

Correct Answer: D

QUESTION 20

- (Topic 4)
Which can be used to determine whether a process is stable or has predictable performance?

Correct Answer: C