QUESTION 121

- (Topic 4)
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Correct Answer: D

QUESTION 122

- (Topic 1)
An element of the project scope statement is:

Correct Answer: A

QUESTION 123

- (Topic 2)
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Correct Answer: D

QUESTION 124

- (Topic 5)
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Correct Answer: A

QUESTION 125

- (Topic 3)
An input of the Control Schedule process is the:

Correct Answer: D