- (Topic 4)
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Correct Answer:
C
- (Topic 4)
Types of internal failure costs include:
Correct Answer:
D
- (Topic 1)
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Correct Answer:
B
- (Topic 1)
Identify Risks is part of which Process Group?
Correct Answer:
A
- (Topic 2)
Which project document is updated in the Control Stakeholder Engagement process?
Correct Answer:
B