- (Topic 4)
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Correct Answer:
B
- (Topic 3)
Which of the following investigates the likelihood that each specific risk will occur?
Correct Answer:
D
- (Topic 4)
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Correct Answer:
C
- (Topic 1)
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Correct Answer:
B
- (Topic 4)
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Correct Answer:
C