QUESTION 66

- (Topic 2)
The following is a network diagram for a project.
PMI-100 dumps exhibit
What is the critical path for the project?

Correct Answer: C

QUESTION 67

- (Topic 5)
A project manager has created an issue log to document issues communicated by project
team members during weekly team meetings. This is an input of:

Correct Answer: A

QUESTION 68

- (Topic 3)
Which Process Group typically consumes the bulk of a project's budget?

Correct Answer: B

QUESTION 69

- (Topic 2)
Which Manage Communications tool or technique focuses on identifying and managing barriers?

Correct Answer: C

QUESTION 70

- (Topic 2)
Those who enter into a contractual agreement to provide services necessary for a project are:

Correct Answer: B